Forms
No
|
Type of Application
|
Form
|
1
|
Application for a License to Use, Work or Operate an Electrical Generating Installation or to Supply Energy |
Form A |
2
|
Application for Registration of an Installation |
Form B |
3
|
Notice of Initial Inspection |
Form E |
4
|
Notice of follow up Inspection |
Form F |
Reference
1. Information required for Financial Analysis.
2. Checklist for supporting document to apply generating licence:
- Application with installed capacity not exceeding 1.5MW in total. click here to download; or
- Application with installed capacity exceeding 1.5MW in total. click here to download.
3. Information for Net Energy Metering (NEM) and Self consumption PV solar installation. Click here to download.
General Requirements
Licence is required for generation of electricity exceeding 5kW or to supply / transmit electricity.
In addition, installations may be registered before a Certificate of Registration is issued and this may include installations issued with a licence.
1. Application for a Licence to Use, Work or Operate an Electrical Generating Installation or to Supply Energy and Registration of Electrical Installation, the following supporting documents are required:
No
|
Documents Required
|
No of Copies
|
Remarks
|
1
|
Form A : Application for a Licence to Use, Work or Operate an Electrical Generating Installation or to Supply Energy under Section 4 of the Electricity Ordinance. |
2 sets
|
Sections 1, 2, and 3 duly completed and signed. |
2
|
Form B : Application for Registration of an Installation |
1 set
|
Duly completed and signed |
3
|
Single-line circuit drawing |
2 sets
|
Scheme of the electrical generation and distribution system to be supplied must be shown. |
4
|
Land Lot Maps
|
6 sets
|
Area / boundary of electricity supply to be outlined. |
5
|
Location Plans |
2 sets
|
Locality of the premises to be shown. |
6
|
Generator technical specifications |
2 sets
|
Schedules showing the technical specifications of the generator units to be installed / operated. |
7
|
Justification / Purpose
|
1 set
|
Reason for self-generation instead of obtaining electricity supply from SESCO. |
8
|
Financial Analysis |
1 set
|
Please refer to the format of Financial Analysis. Does not apply to standby generator application. |
9
|
Other documents |
|
Any other supporting document as requested. |
2.Application for Registration of Electrical Installations, the following supporting documents are required:
No
|
Documents Required
|
No of Copies
|
Remarks
|
1
|
Form B : Application for Registration of an Installation |
1 set
|
Sections 1, 2, and 3 duly completed and signed. |
2
|
Single-line circuit drawing |
2 sets
|
Scheme of the electrical generation and distribution system to be supplied must be shown. |
3
|
Location Plans
|
2 sets
|
Locality of the premises to be shown. |
4
|
Other documents |
|
Any other supporting document as requested. |
Note: In accordance to Rule 64 of the Electricity Rules, 1999, all plans, drawings and specifications shall be prepared and submitted by a Competent Person.
Licence Fees
Installation Capacity
|
Function of Installation
|
Generation
|
Transmission
|
Distribution
|
Where the aggregate power does not exceed 5 KW |
NIL
|
NIL
|
NIL
|
Where the aggregate power is 5 KW and above but less than 100 MW |
80sen/KW
|
80sen/KW
|
50sen/KW
|
Where the aggregate power is 100 MW and above |
RM1.00/KW
|
RM1.00/KW
|
50sen/KW
|
Incalculation of the total fee :
(a) KW is taken as 0.8 x kVA;
(b) Where a license is given for two or more activities, the licensee is only required to pay the higher fee.
(c) The minimum fee for any installation is RM100.00.
Licence Fees For Construction and Maintainence of Installation and Generation of Electricity By Hydro Power
(a) Prior to the date of commercial operation of the installation:
Installation Capacity
|
Fee Per Annum
|
100 MW and below
|
RM100
|
Between 101 MW and 500 MW
|
RM1,000
|
Between 501 MW and 999 MW
|
RM50,000
|
1000 MW and above
|
RM100,000
|
(b) After the date of commercial operation of the installation:
Installation Capacity
|
Fee Per Annum
|
100 MW and below
|
RM0.50 per KW
|
Between 101 MW and 500 MW
|
RM1.00 per KW
|
Between 501 MW and 999 MW
|
RM1.20 per KW
|
1000 MW and above
|
RM1.50 per KW
|
(c) |
For the purpose of this item, the "date of commercial operation" shall mean the date on which the Licensee commences generation of electricity for sale and delivery to the public.
|
|
|
(d) |
The provisions of this item shall not apply where the generation of electricity by hydro-power is covered under the terms of a Licence for which fees are chargeable and paid under Part III (A) of the Second Schedule.
|
Fees for Registration of Installation and Renewal
Fees according to the following fees shall be payable for the registration installation or renewal of registration:
|
Capacity of Installation
|
Fee for 12 months
|
(a)
|
for each installation of 10 kilowatts or less
|
RM20
|
(b)
|
for each installation above 10 kilowatts to 50 kilowatts
|
RM50
|
(c)
|
for each installation above 50 kilowatts to 100 kilowatts
|
RM500
|
(d)
|
for each installation above 50 kilowatts to 100 kilowatts
|
RM1,000
|
(e)
|
for each installation above 300 kilowatts to 600 kilowatts
|
RM1,500
|
(f)
|
for each installation above 600 kilowatts to 1000 kilowatts
|
RM2,000
|
(g)
|
for each installation above 1000 kilowatts to 2500 kilowatts
|
RM3,000
|
(h)
|
for each installation above 2500 kilowatts to 5000 kilowatts
|
RM5,000
|
(i)
|
for each installation above 5,000 kilowatts
|
RM1.00 per kilowat
|
Procedures to Apply For a Licence
Procedures for Registration of Installation
|