EIU - Licensing & Registration Of Installations

 

EIU - Licensing & Registration of Installations



Forms

No
Type of Application
Form
1
Application for a License to Use, Work or Operate an Electrical Generating Installation or to Supply Energy Form A
2
Application for Registration of an Installation Form B
3
Notice of Initial Inspection Form E
4
Notice of follow up Inspection Form F


Reference

1. Information required for Financial Analysis.

2. Checklist for supporting document to apply generating licence:

  • Application with installed capacity not exceeding 1.5MW in total. click here to download; or
  • Application with installed capacity exceeding 1.5MW in total. click here to download. 
3. Information for Net Energy Metering (NEM) and Self consumption PV solar installation. Click here to download. 
 

General Requirements

Licence is required for generation of electricity exceeding 5kW or to supply / transmit electricity.

In addition, installations may be registered before a Certificate of Registration is issued and this may include installations issued with a licence.

1. Application for a Licence to Use, Work or Operate an Electrical Generating Installation or to Supply Energy and Registration of Electrical Installation, the following supporting documents are required:

No
Documents Required
No of Copies
Remarks
1
Form A : Application for a Licence to Use, Work or Operate an Electrical Generating Installation or to Supply Energy under Section 4 of the Electricity Ordinance.
2 sets
Sections 1, 2, and 3 duly completed and signed.
2
Form B : Application for Registration of an Installation
1 set
Duly completed and signed
3
Single-line circuit drawing
2 sets
Scheme of the electrical generation and distribution system to be supplied must be shown.
4

Land Lot Maps

6 sets
Area / boundary of electricity supply to be outlined.
5
Location Plans
2 sets
Locality of the premises to be shown.
6
Generator technical specifications
2 sets
Schedules showing the technical specifications of the generator units to be installed / operated.
7

Justification / Purpose

1 set
Reason for self-generation instead of obtaining electricity supply from SESCO.
8
Financial Analysis
1 set
Please refer to the format of Financial Analysis. Does not apply to standby generator application.
9
Other documents   Any other supporting document as requested.
 

2.Application for Registration of Electrical Installations, the following supporting documents are required:

No
Documents Required
No of Copies
Remarks
1
Form B : Application for Registration of an Installation
1 set
Sections 1, 2, and 3 duly completed and signed.
2
Single-line circuit drawing
2 sets
Scheme of the electrical generation and distribution system to be supplied must be shown.
3

Location Plans

2 sets
Locality of the premises to be shown.
4
Other documents   Any other supporting document as requested.

Note: In accordance to Rule 64 of the Electricity Rules, 1999, all plans, drawings and specifications shall be prepared and submitted by a Competent Person.


Licence Fees
 
Installation Capacity
Function of Installation
Generation
Transmission
Distribution
Where the aggregate power does not exceed 5 KW
NIL
NIL
NIL
Where the aggregate power is 5 KW and above but less than 100 MW
80sen/KW
80sen/KW
50sen/KW
Where the aggregate power is 100 MW and above
RM1.00/KW
RM1.00/KW
50sen/KW


Incalculation of the total fee :

(a) KW is taken as 0.8 x kVA;

(b) Where a license is given for two or more activities, the licensee is only required to pay the higher fee.

(c) The minimum fee for any installation is RM100.00.

 

Licence Fees For Construction and Maintainence of Installation and Generation of Electricity By Hydro Power

(a) Prior to the date of commercial operation of the installation:

Installation Capacity
Fee Per Annum
100 MW and below
RM100
Between 101 MW and 500 MW
RM1,000
Between 501 MW and 999 MW
RM50,000
1000 MW and above
RM100,000

(b) After the date of commercial operation of the installation:
 
Installation Capacity
Fee Per Annum
100 MW and below
RM0.50 per KW
Between 101 MW and 500 MW
RM1.00 per KW
Between 501 MW and 999 MW
RM1.20 per KW
1000 MW and above
RM1.50 per KW
 
(c)
For the purpose of this item, the "date of commercial operation" shall mean the date on which the Licensee commences generation of electricity for sale and delivery to the public.
   
(d)

The provisions of this item shall not apply where the generation of electricity by hydro-power is covered under the terms of a Licence for which fees are chargeable and paid under Part III (A) of the Second Schedule.

 

Fees for Registration of Installation and Renewal

Fees according to the following fees shall be payable for the registration installation or renewal of registration:

 
Capacity of Installation
Fee for 12 months
(a)
for each installation of 10 kilowatts or less
RM20
(b)
for each installation above 10 kilowatts to 50 kilowatts
RM50
(c)
for each installation above 50 kilowatts to 100 kilowatts
RM500
(d)
for each installation above 50 kilowatts to 100 kilowatts
RM1,000
(e)
for each installation above 300 kilowatts to 600 kilowatts
RM1,500
(f)
for each installation above 600 kilowatts to 1000 kilowatts
RM2,000
(g)
for each installation above 1000 kilowatts to 2500 kilowatts
RM3,000
(h)
for each installation above 2500 kilowatts to 5000 kilowatts
RM5,000
(i)
for each installation above 5,000 kilowatts
RM1.00 per kilowat
 

Procedures to Apply For a Licence



Procedures for Registration of Installation

 

 
image Announcement